§ 52.022. REPORT AFTER FINAL COMPLIANCE.
Latest version.
- Within 90 days following the date for final compliance with applicable pretreatment standards or in the case of a new source following commencement of the introduction of wastewater into the POTW, any industrial user subject to pretreatment standards and requirements shall submit to the Authority Manager a report containing the information described in § 52.019(B)(4), (B)(5), and (B)(6). This report shall include the user’s actual production during the appropriate sampling period.(1995 Code, § 58-273) (Ord. passed 5-22-1995)